Projects

NATIONAL HIGHWAY 1 DEO CA – KHANH HOA

Total Invest-ment $100.3 million
Route Length 37.7 km (including 18 bridges)
Implementation Period 2012 - 2015
The Role Construction survey, detailed design, construction supervision consultancy
Status Completed

DEO CA TUNNEL

Total Invest-ment $431.6 million
Route Length 13.5 km (including approach roads)
Implementation Period 2010 - 2017
The Role Construction survey, detailed design, construction supervision consultancy
Status Completed

HAI VAN TUNNEL

Total Invest-ment $276.8 million
Route Length 12.4 km (including approach roads)
Implementation Period 2017-2021
The Role  Supervision consultancy, project management consultancy
Status Completed

BAC GIANG – LANG SON EXPRESSWAY

Total Invest-ment $462.4 million
Route Length  64.9 km
Implementation Period 2018 - 2020
The Role Supervision Consultancy.
Status Completed

TINH YEU BRIDGE

Total Invest-ment $80.0 million
Route Length 4,3 km
Implementation Period 2020 - 2022
The Role Survey, feasibility study report, technical design
Status Completed

BINH MINH BRIDGE

Total Invest-ment $64.5 million
Route Length 4,3 km
Implementation Period 2020 - 2022
The Role 2.6 km with 6 lanes for mo-tor vehicles
Status Completed

HO CHI MINH CITY RING ROAD 4 – PHASE 1

Total Invest-ment $445.4 million
Route Length 47,45 km
Implementation Period 2024 - 2028
Design Speed 100 km/h
The Role Survey, feasibility study report, supervision consultancy

BIEN HOA – VUNG TAU EXPRESSWAY PROJECT

Total Invest-ment 818.96 million USD
Route Length 53.7 kilometers
Project classification Roads: Grade I; Bridges: Grade II
The Role Technical Design
Status Completed.

TRUNG LUONG – MY THUAN EXPRESSWAY, PHASE 1

Total Invest-ment 12.668 tỷ đồng
Route Length 51,5 km
Project classification Roads: Grade I; Bridges: Grade II; Civil Structures: Grade II; Technical Infrastructure: Grade II
The Role Construction Survey, Construction Design, Supervision Consultancy, Project Management Consultancy
Status Completed.

CAM LAM – VINH HAO PROJECT

Total Invest-ment 337.44 million USD
Route Length 78.5 kilometers
Project classification Roads: Grade II; Bridges: Grade II
The Role Supervision Consultancy.
Status Completed

UPGRADE AND EXPANSION OF PRENN PASS

Total Invest-ment 20.97 million USD
Route Length 7.37 kilometers
Project classification Roads: Grade II; Bridges: Grade II
The Role Construction Survey, Preparation of Technical Feasibility Report
Status Completed

DAI NGAI BRIDGE

Total Invest-ment 148.13 million USD
Route Length  15.1 km (Bridge 1 approximately 2.6 km; Bridge 2 approximately 0.9 km)
Project classification Bridge of Special Grade
The Role Construction Survey, Technical Design
Status Completed

EXPANSION OF CAM LO - LA SON EXPRESSWAY

Total Investment 267.7 million USD
Route Length 98 km
Project Location Hue City, Quang Tri Province
Project Classification Grade II Transport Infrastructure Project
Project Owner Ho Chi Minh Road Project Management Board
A2Z's Role Technical Design Survey
Implementation Period 2025
Status Completed

MAI SON – NATIONAL HIGHWAY 45 EXPRESSWAY

Total Invest-ment 459.18 million USD
Route Length 63.4 kilometers
Project classification Roads: Grade I; Bridges: Grade II
The Role Supervision Consultancy
Status Supervision in Progress

CHI THANH – VAN PHONG EXPRESSWAY

Total Invest-ment 409.48 million USD
Route Length 48 kilometers
Project classification Roads: Grade I; Bridges: Grade II
The Role Supervision Consultancy
Status Supervision in Progress

VUNG ANG – BUNG PROJECT

Total Invest-ment 473.93 million USD
Route Length  
Project classification Roads: Grade I; Bridges: Grade II; Civil Structures: Grade II; Technical Infrastructure: Grade II
The Role  Supervision Consultancy
Status Supervision in Progress

QUANG NGAI – HOAI NHON PROJECT

Total Invest-ment 773.46 million USD
Route Length 88 kilometers
Project classification
 Roads: Grade I; Bridges: Grade II; Tunnel: Special; Civil Structures: Grade II; Technical Infrastruc-ture: Grade II
The Role Supervision Consultancy
Status Supervision in Progress

BAC AI PUMPED STORAGE HYDROPOWER PROJECT

Total Invest-ment 800 million USD
Route Length -
Project classification Tunnel: Grade I
The Role Supervision Consultancy
Status Supervision in Progress

BAC GIANG – LANG SON EXPRESSWAY, HUU NGHI – CHI LANG BORDER GATE SEGMENT

Total Invest-ment 819.53 million USD
Route Length 43 km
Project classification  Roads: Grade I; Bridges: Grade II; Civil Structures: Grade II; Technical Infrastructure: Grade II
The Role

Preparation of Technical Feasibility Report, Construction Supervision Consulting

Status Supervision Consultancy in Progress

DONG ĐANG – TRA LINH EXPRESSWAY

Total Invest-ment 543.36 million USD
Route Length 121 kilometers
Project classification Roads: Grade I; Bridges: Grade I; Civil Structures: Grade II;
The Role Construction Survey, BIM, Preparation of Technical Feasibility Report, and Supervision Consultancy
Status Supervision Consultancy in Progress

CHO MOI – BAC KAN ROUTE

Total Invest-ment 218 million USD
Route Length -
Project classification Roads: Grade I; Bridges: Grade II
The Role Survey and Technical Design
Status Currently Under Implementation

CONNECTOR ROUTE BETWEEN THE CITY AND THE DONG DANG – TRA LINH EXPRESSWAY

Total Invest-ment 56.76 million USD
Route Length 31 kilometers
Project classification Roads: Grade I; Bridges: Grade I; Civil Structures: Grade II; Technical Infrastructure: Grade II
The Role Construction Survey, BIM, Preparation of Technical 
Status Pre-Feasibility Study in Progress

DONG DANG – TRA LINH – TA LUNG BORDER GATE EXPRESSWAY

Total Invest-ment 75.83 million USD
Route Length -
Project classification Roads: Grade I; Bridges: Grade II
The Role Construction Survey, BIM, Preparation of Technical 
Status Feasibility Study in Progress

NORTH–SOUTH EXPRESSWAY SERVICE AREA PROJECT

Total Invest-ment 113.74 million USD
Route Length -
Project classification  Roads: Grade III; Civil Structures: Grade II; Technical Infrastructure: Grade II
The Role Construction Survey, BIM, Preparation of Technical Feasibility Report, Architectural Documentation, Preparation of Technical Design and Construction Drawings
Status Pre-Feasibility Study in progress

DONG DANG – TRA LINH EXPRESSWAY SERVICE AREA

Total Invest-ment 1,042.09 million USD
Route Length -
Project classification Roads: Grade I; Bridges: Grade I; Tunnel: Grade I; Civil Structures: Grade I; Technical Infrastruc-ture:
The Role Supervision Consultancy
Status Pre-Feasibility Study in progress

VUNG ANG – TAN AP – MU GIA RAILWAY LINE

Total Invest-ment 56.87 million USD
Route Length 103 km
Project classification Technical Infrastructure: Class II
The Role Construction Survey, BIM, Preparation of Technical Feasibility Report, Architectural Documentation, Preparation of Technical Design and Construction Drawings
Status Pre-Feasibility Study in progress

MOC CHAU – SON LA EXPRESSWAY, PHASE 2

Total Invest-ment 844 million USD
Route Length 88 km
Project classification Roads: Grade I; Bridges: Grade II
The Role Supervision Consultancy
Status Pre-Feasibility Study in progress

SON TRIEU TUNNEL, PART OF THE QUY NHON – CHI THANH SECTION PROJECT

Total Invest-ment  301.88 million USD
Route Length -
Project classification Tunnel: Grade II
The Role Construction Design
Status Technical Design and Construction Drawing Preparation in Progress

KHANH HOA – BUON MA THUOT EXPRESSWAY, PHASE 1

Total Invest-ment  213.54 million USD
Route Length -
Project classification Roads: Grade I; Bridges: Special; Tunnel: Grade II
The Role Construction Survey, Preparation of Technical Feasibility Report, Con-struction Design, and Supervision Consultancy
Status In progress of Preparing the Tech-nical Design and Con- struction Draw-ings

HOA BÌNH – MOC CHAU EXPRESSWAY

Total Invest-ment 379.03 million USD
Route Length 85 kilometers
Project classification Tunnel: Grade II
The Role Technical Design, Preparation of Construction Drawings for Tunnel No. 3 and Tunnel No. 4
Status
Technical Design and Construction Drawing Preparation in Progress

TAN PHU – BAO LOC EXPRESSWAY

Total Invest-ment  682.46 million USD
Route Length 66 kilometers
Project classification Roads: Grade I; Bridges: Grade II
The Role Construction Survey, BIM, Preparation of Feasibility Report, Technical Design, Supervision Consultancy
Status Technical Design in Progress

ROAD TUNNEL THROUGH HOANG LIEN PASS

Total Invest-ment 125.12 million USD
Route Length -
Project classification
Roads: Grade III; Bridges: Special; Tunnel: Special; Civil Structures: Grade II; Technical Infrastruc-ture: Grade II
The Role Construction Survey, BIM, Preparation of Feasibility Report, Technical Design, Supervision Consultancy
Status Technical Design in Progress

HO CHI MINH CITY – TRUNG LƯƠNG – MY THUAN EXPRESSWAY

Total Invest-ment 1,509 million USD
Route Length 96 kilometers
Project classification Roads: Grade I; Bridges: Grade II
The Role Construction Survey, BIM, Technical Design, and Supervision Consultancy
Status Final Feasibility Study Report Submission in Progress

TUYEN QUANG – HA GIANG EXPRESSWAY (PHASE 2)

Total Invest-ment 563.11 million USD
Route Length 77 kilometers
Project classification Roads: Grade I; Bridges: Grade II
The Role Construction Survey, BIM, Preparation of Technical Feasibility Report, Architectural Documentation, Preparation of Technical Design and Construction Drawings
Status
Awaiting Approval of the Revised Technical Feasibility Report